Analytical Chemistry Trinidad & 

Tobago Lab Resources

GAS CHROMATOGRAPHY TROUBLESHOOTING


Search this site

HOME Email about






Excessive Baseline Noise


Possible Cause Solution Comments
Injector contamination clean the injector gas lines may need cleaning
Column contamination Bakeout the column
Solvent rinse the column
Limit bakeout to 2 hrs.
Bonded and crosslinked phases only
Detector contamination clean the detector noise increases over time, and not suddenly
Contaminated or low quality gases use better grade gases
check for gas leaks and expired gas traps
usually occurs after changing a gas cylinder
Incorrect detector gas flow rates adjust flow rates to recommended values consult literature
Leak when using MS, ECD, or TCD find and eliminate the leak usually at the column fittings or injector
Old detector filament, lamp, or multiplier replace appropriate part use new part
Un-equilibrated detector allow detector to stabilize may require up to 24 hrs to fully stabilize
Incompletely conditioned column fully condition column critical for trace level analyses

Change in Peak Size


Possible Cause Solution Comments
Change in detector response Check gas flows, temperatures, and settings.Check background level or noise All peaks may not be equally affected.May be caused by system contamination and not the detector
Co-elution Change column temperature or stationary phase Decrease column temperature and check for appearance of a peak shoulder or tail
Change in the purge activation time Check the purge activation time For splitless injection
Change in the injection volume Check injection technique Injection volumes are not linear
Change in sample concentration Check and verify sample concentration Sample degradation, variances in sample temperature or ph
Leak in the syringe Use a different syringe Sample leaks passed the plunger or around the needle, Leaks are often not readily visible
Column contamination Trim the column
Solvent rinse the column
Remove about half to 1 meter from the front of the column. Only bonded and crosslinked phases
Column activity Irreversible Only affects active compounds

Tailing Peaks


Possible Cause Solution Comments
Column contamination Trim the column
Solvent rinse the column
Trim half to 1 meter from the front of the column
Only for bonded and crosslinked phases
Column activity Irreversible Only affects active compounds
Solvent-phase polarity mismatch Change sample solvent
Install a retention gap
More tailing for the eluting peaks, or those closest the solvent front
3 to 5 meter retention gap is sufficient
Solvent effect violation for splitless or on-column injections Decrease the initial column temperature Peak tailing decreases with retentiongas lines may need cleaning
Too low of a split-ratio Increase the split-ratior Flow from split vent should be 20ml / min or higher
Poor column installation Reinstall the column More tailing for the early eluting peaks
Some active compounds always tail None Most common for amines and carboxylic acids

Retention Time Shift